Services Provided
Continuum successfully developed and submitted a business case for Parc Pelenna to support the planning application submitted for the 53-unit scheme. The business case covered the following areas:
Evidence of demand and sales values;
Main competitors;
Product differentiation;
Tourism strategy;
Price and promotion;
Socio-economic benefits;
Job creation;
Cost and financial projections;
Finance;
Development appraisal and cashflow modelling; and
Profitability
Outputs
The business case was successfully submitted to Neath Port Talbot planning authority in July 2019 and was subsequently approved as part of the wider planning application for the 53-unit scheme. Continuum are currently working closely with Trivselhus to assist with the delivery phase of the project.